Walters Power International, through its affiliate, PPR has originated and developed a 50MW power plant in Pakistan. This plant is powered by two Rolls Royce RB211 gas turbine generators. This power plant is the second completed where WPI sourced the equipment, negotiated and administered the EPC, Start Up and Commissioning and the O&M agreements.
A 50 MW expansion of Naudero I was planned and negotiated as Naudero II. Power Purchase Agreements were negotiated, and an adjoining site was secured, and the engineering was completed for Naudero II. WPI sourced the equipment, from New York by purchasing a plant with LM5000 turbines and these units were disassembled and shipped to Pakistan. The country discontinued the expansion program shortly after the shipping of equipment and Naudero II was not constructed and the equipment was salvaged. [need to find a picture of the equipment on a ship…DS may know where to find].